How the Annina Hänny school building came into being
On 31st August 2016, the exceptionally popular English teacher at Berufsschule Lenzburg vocational school, Annina Hänny-Schulz, died of breast cancer at the age of 55.
Gone too soon, Annina was a member of the “Soroptimist International Club Lenzburg” association for women. It was there that Annina Hänny met Regina Nasseremba, founder of Beatrice Secondary School Kyankwanzi in Uganda. Annina and Regina got on very well and became friends. The Hänny family therefore decided to support the school in Uganda with the donations from the condolences fund. The condolences expressed for Annina Hänny were overwhelming, and a record sum of money was collected in her memory. With the total sum of 26,000 Swiss Francs, School Principal Regina decided to create a lasting memorial. She subsequently laid the foundation stone for the Annina Hänny school building, which has several floors and will help cover the school’s capacity requirements for many years to come. The initial ground-breaking ceremony for the new school building took place on 8th July 2018. After seven years of construction and with the support of the Hänny family and other generous sponsors, the house was officially opened on May 22, 2025, in the presence of the Hänny family.
Opening ceremony Annina Hänny school building
May 22, 2025








Work on the surroundings
February 21, 2025






The last sanitary facilities are connected to the pipes
February 21, 2025





Watertanks on top of Annina Hänny schoolhouse
November 12, 2024


The Annina Hänny school building during the day and at night. It is labeled and illuminated
August 20, 2024








Painting and plumbing work
May 21, 2024










Staff meeting in the AH-building
October 19, 2023


The Annina Hänny school building is illuminated
July 24, 2023




Working on the floor of the Annina Hänny school building
September 11, 2022



Stair and balcony railings are installed
February 7, 2022




AH schoolblock without scaffolding
September 2, 2021












Exavation for bio digester
July 3, 2021





AH schoolblock construction progress
May 28, 2021



AH schoolblock construction progress
May 2, 2021


AH schoolblock construction progress
April 23, 2021




AH schoolblock construction progress
March 16, 2021









Rainwater channels
February 24, 2021
A storm water problem that has existed for a long time is currently being fixed on the school grounds. Because the land slopes gently, soil is washed out and across the site during heavy rains. This means there is red earth everywhere, slippery, soggy paths, and discoloured building walls. Now canals are being built through which the water can flow off in an orderly manner. These will remain open. Regina will plant bushes around the edges to prevent animals from stepping in them.




AH schoolblock construction progress
September 23, 2020




AH schoolblock construction progress
July 06, 2020









AH schoolblock construction progress
March 18, 2020



AH schoolblock construction progress
December 3, 2019






Building the groundfloor walls
October 16, 2019
The floor space will be constructed into classrooms only now.




Celebration in the groundfloor
October 15, 2019








AH schoolblock construction progress
October 4, 2019





Annina Hänny schoolblock
April 4, 2019





Annina Hänny block groundwork
September 7, 2018






Breaking and blessing of the ground for Annina Hänny classroom and administration block
July 9, 2018